County Road 42 Reconstruction to Resume in the Spring

Significant progress has been made on the first phase of major improvements to the County Road 42 corridor between County Road 19 (Manning Road) and the City of Windsor.

Phase 1 construction has concluded for the winter with the following work completed:

  • Temporary widening of the roadway;
  • Creation of temporary sidewalks;
  • Relocation of water lines and fire hydrants;
  • Construction of temporary drainage infrastructure;
  • Installation of a new main sanitary sewer line and connections;
  • Installation of a storm sewer, connections and an outlet at Pike Creek;
  • Erection of poles for temporary traffic signals at Lesperance Road;
  • Placement of temporary asphalt on road shoulders; and
  • Clean up and demobilization for the winter shutdown.

Work on Phase 1 of the County Road 42 corridor reconstruction will resume in the spring, with more detailed updates to be provided closer to the recommencement of construction.

The work for Phase 1 construction between Concession 11 and Pike Creek will allow for the creation of two roundabouts, roadway widening of County Road 42 and re-alignment of County Road 43, all of which will take place during future phases.

Up-to-date information about all phases of this major, multi-year project that will increase road capacity and enhance neighbourhood connectivity can be found at countyofessex.ca/CR42. Those requiring more details, can contact County of Essex Infrastructure and Planning Services at engineering@countyofessex.ca.